HVAC Restoration saves $1 million dollars in capital budget at the University of Texas, San Antonio with refurbishment of two air handler units (AHUs).

Challenge

The University of Texas San Antonio (UTSA) faced ongoing maintenance issues with two large air handler units (AHUs): AHU 23 S-7 and AHU 24 S-8. After years of wear and tear, the AHUs started to severely deteriorate.

Eventually, the axle that drives the blower wheel broke and needed to be replaced. Because of this, there was no airflow or ventilation being supplied in the UTSA Convocation Center.

UTSA decides to restore air handler units (AHUs)

UTSA decided to restore the AHUs with the Higher Education Emergency Relief Fund (HEERF)

UTSA decided to restore the AHUs with the Higher Education Emergency Relief Fund (HEERF), provided by the Education Stabilization Fund (ESF), through the Coronavirus (COVID-19) Aid, Relief, and Economic Security (CARES) Act.

This presented a challenge because of the looming deadline to use the funds. From the time of the purchase order partnering with Grainger, WTI/Pure Air Control Services only had 30 days to order equipment (including fan arrays), mobilize, complete all work, and invoice the project.

Solution

WTI/Pure Air Control Services came into this project with a very small window to complete the total HVAC restoration work. 

But with the well-rounded team of Grainger, Tremco, and UTSA, WTI/Pure Air Control Services were able to make the project a total success. The following services were executed on both AHUs.

HVAC New Life Restoration

HVAC New Life is a series of component services conducted over consecutive nights that effectively cleans and restores an AHU without loss of supply air during normal operating hours.

PURE-Steam AHU and Coil Cleaning

The first step was to environmentally remove any old and contaminated fiberglass insulation

The first step was to environmentally remove any old and contaminated fiberglass insulation. After that, the units were thoroughly HEPA-vacuumed of residual debris.

Next, airflow resistance readings were taken across the cooling coils. This is known as a Coil Cleanliness Verification test, or CCV. Then the interior of the unit was masked off and sanitized with WTI Pure Air’s proprietary PURE-Steam process.

This included a deep cleaning of the cooling coils as well. PURE-Steam utilized bio-enzyme treatments and high temperature, low-pressure steam to penetrate through debris lodged in the coil. CCV readings were also taken after the cleaning. This process improves AHU performance and indoor air quality.

Blower Removal and New Fan Array

The next step was to remove the old blower assemblies and motors. Then the new fan array that was re-engineered specifically for each AHU was installed. First, the pre-built bulkhead wall was secured into place.

Then the fans are fitted into their channel locks and wired for service. Fan array retrofits provide improved efficiency and redundancy since there are no more bearings, belts, or shivs to maintain.

Sheet Metal Fabrication and New Access Doors

Years of condensation in the two AHUs corroded and structurally compromised their floors. These areas were removed, secured and new sheet metal flooring panels were installed. External doors were also installed for ease of access and future maintenance.

High Performance Coatings and Fiberglass Free Insulation

The entire process is completed with the installation of new, fiberglass-free insulation

The final step in the HVAC New Life restoration process includes refinishing the metal components of the units with high performance coatings that are corrosion resistant, flexible, and very low VOC. This includes relining the drain pans with a multi-part polyurethane coating that is designed and tested for HVAC systems.

The entire process is completed with the installation of new, fiberglass-free insulation that is moisture resistant to prevent future degradation.

Pure Air Control Services Help restore AHUs

In summary, WTI/Pure Air Control Services helped restore the two AHUs for the Convocation Center within one month, whereas new units would have taken more than 30 weeks to procure, deliver and install.

UTSA saved $1,083,000 in capital expenditure (CAPEX) by restoring the AHUs instead of replacing them, and static pressure performance was improved by 18%, which can directly help with energy savings over time. All in all, UTSA now has peace of mind in two restored units with five-year warranties on the fans and the coatings that will provide many more years of services for the convocation center.

Download PDF version Download PDF version

In case you missed it

LG Accelerates B2B Growth With Key Structural Changes
LG Accelerates B2B Growth With Key Structural Changes

LG Electronics (LG) announced a series of organizational changes and executive appointments following the approval of its board of directors. This restructuring aims to accelerate...

Shortwave Infrared Heating: SWIR: The Smart Choice For Warehouse Heating
Shortwave Infrared Heating: SWIR: The Smart Choice For Warehouse Heating

For warehouse and factory owners, cutting their heat energy bills by over 90% might seem like a pipedream. I’ve been in enough warehouses to know one thing: heating them is e...

Genea And Siemens Partner To Enhance Physical Security Solutions
Genea And Siemens Partner To Enhance Physical Security Solutions

Siemens and Genea recently announced a second collaborative effort to provide security professionals and facility managers with improved security using the cloud. The security so...

vfd