Download PDF version

Aggreko is proud to announce that they have completed commissioning of the largest flare gas to power project in the Middle East to date, with 165 MW capacity. The plant is situated nearby the Saqala Field, Garmain block, in South East Kurdistan.

The 165 MW modular power plant has run at full capacity for 72 hours in the project’s final site acceptance test (SAT), marking successful on-time, on-budget delivery.

Flare gas to power project

The plant is run on approximately 40 million square cubic feet (SCF) per day of associated petroleum gas (APG) from the Saqala Field, saving 840 tons of CO2 per day, and cutting flaring by a third.

Delivered over the course of 2020-2021 against the backdrop of the COVID-19 pandemic, the project was conceived and executed in close collaboration with Kurdistan’s Ministry of National Resources (MNR) and Ministry of Electricity (MOE).

New gathering pipeline to transport the APG

Aggreko also delivered a new 6 km gathering pipeline to transport the APG to the power plant

Aggreko also delivered a new 6 km gathering pipeline to transport the APG to the power plant, and upgraded 7km of 33 kV and 33km of 132 kV overhead cables to new high tensile low sage (HTLS) conductors in order for the local distribution grid to handle the new power plant’s full output.

Ahmed Mufti, the Kurdistan Regional Government’s Deputy Minister of Natural Resources (MNR) said, “We worked with Aggreko to provide a creative solution to convert flare gas to power in a way that directly benefits the local population and the region in general, while creating a positive environmental impact and improving air quality.

Middle East’s largest flare gas to power project

Phil Burns, Managing Director for Aggreko Middle East, comments “Kurdistan’s Regional Government has been forward-thinking in looking for ways to capture and convert gas that would otherwise be flared, to unlock production and power the local economy.

Phil Burns adds, “We are extremely proud to have worked with the Ministries to deliver the Middle East’s largest flare gas to power project to date, while upgrading the local infrastructure to the lasting benefit of the community and businesses it serves.

Plant built using 192 MW of modular gas generators

The project is now contracted to run for four years, delivering power 24/7/365. Built using 192 MW of modular gas generators, the plant can easily be scaled up or down in response to changing gas volumes.

Approximately 60 Aggreko engineers have delivered the project, with 80 local jobs created directly and indirectly for the site's delivery and ongoing operation, including 44 local nationals who have already commenced Aggreko's official training scheme.

Download PDF version Download PDF version

In case you missed it

Johnson Controls On Financial Times Europe Climate Leaders List
Johnson Controls On Financial Times Europe Climate Leaders List

Johnson Controls, the global pioneer for smart, healthy and sustainable buildings, has again been named to the Financial Times Europe Climate Leaders list in 2024. This marks...

How Finalized SNAP Rule 26 Will Impact Uses Of Commercial Refrigerants
How Finalized SNAP Rule 26 Will Impact Uses Of Commercial Refrigerants

SNAP Rule 26 marks an important milestone in the transition from commercial refrigeration to new refrigerants. The rule lists refrigerant substitutes that provide a spectrum of tec...

Carrier Cooling-As-A-Service For Enhanced HVAC Solutions
Carrier Cooling-As-A-Service For Enhanced HVAC Solutions

Carrier is pleased to announce Carrier Cooling-as-a-Service, a portfolio of innovative solutions to help commercial customers simplify the operation of HVAC and other thermal or el...

vfd