25 Jan 2023

Dunamenti ordered a 30MW High Voltage Electrode Boiler for Hot water with a 22kV connection for their Power Plant close to Budapest. The electrical boiler will have a design pressure of 11 barg and a design temperature of 187°C.

PARAT will deliver Control Panel and do the Start-Up, Commissioning, Training, and Test Run. The system will be up and running in late summer 2023. The boiler will reduce emissions and bring flexibility to their boiler house.

Dunamenti

Their main area of activity at Dunamenti Erőmű (Dunamenti Erőmű Power Plant) is the production of electricity; however, they also hold a license to trade electricity and gas.

It is the largest gas-fired power plant in the Hungarian electricity system, with a total output of 794 MW. With units which can be started upon demand, it is an active player in the electricity-producing and energy-trading market, well-recognized for its technological reliability.